Specializing in Large Steel Fabrication and Machining

BC Ferries Floating Pontoon

Marine Structures

Installing guardrails.
Installing guardrails. February 12, 2009
  • Description: a floating working pontoon for BCFS
  • Size: 100 ton – 56′ x 50′
  • Finish: Painted
  • Time frame: Six weeks

We worked two ten hour shifts seven days a week to meet the schedule. Panels were fabricated in our main fabrication shop and then moved to our assembly hall to be put together. Painting was done in house by Point Hope Maritime. The finished pontoon was moved onto Point Hope’s marine railway to be launched into the water. Click on the progress pictures below.

Contact Us

We’d love to hear from you.

United Engineering

250-385-9738
info@unitedengineering.ca

Office Hours: 7:30am – 4:00pm Monday to Friday

Main Address
2066 Henry Avenue West
Sidney, BC V8L 5Y1

Satellite Address
327G Harbour Road
Victoria, BC V9A 3S2

Contact Form

Request a Quote

Give us a call or fill out the form below and we will get back to you.

    All fields are required.

    Location + Hours

    Office Hours: 7:30am – 4:00pm Monday to Friday

    We have expanded our business! Our main office is now located at 2066 Henry Avenue West in Sidney, BC. Open in Google Maps ›

    Our satellite location is at 327G Harbour Road in Victoria, BC. Open in Google Maps ›