BC Ferries Floating Pontoon
Marine Structures

- Description: a floating working pontoon for BCFS
- Size: 100 ton – 56′ x 50′
- Finish: Painted
- Time frame: Six weeks
We worked two ten hour shifts seven days a week to meet the schedule. Panels were fabricated in our main fabrication shop and then moved to our assembly hall to be put together. Painting was done in house by Point Hope Maritime. The finished pontoon was moved onto Point Hope’s marine railway to be launched into the water. Click on the progress pictures below.
Welding the top deck plate middle section together. January 19, 2009 Welding stiffeners to the top deck plate middle section. Bottom plate is on the floor. January 22, 2009 Flat section fabrications stacked on one another in main shop. January 27, 2009 Welding bottom plate sections together in assembly hall. January 28, 2009 Outer shell walls in place. Looking at aft end. January 30, 2009 Bulkheads in place. February 3, 2009 Overall view of curved aft end. February 3, 2009 Main deck sections nearing completion. February 4, 2009 Shell and bulkheads in place. Waiting for main deck. February 4, 2009 Installing starboard main deck plate. February 5, 2009 Main deck installed. Welding aft end rub bars. February 11, 2009 Pontoon painted with bollards, railings, and anodes. Man doors have been sealed and primed. February 18, 2009 The end wall of the assembly hall removed and the pontoon being hauled out. February 24, 2009 The pontoon outside the assembly hall. February 24, 2009 The marine railway is located on the other side of the assembly hall. The Pontoon is too large to go around the hall so it was driven onto a barge and moved by water. February 24, 2009 Pontoon on marine railway transfer car. February 25, 2009 Pontoon on marine railway turntable about to be pushed onto the cradle for launching. February 25, 2009 Pontoon lowered into the water by the marine railway cradle and touching the water for the first time. February 25, 2009